Alba Mineral Resrcs. - Investee Company Update
Released
Released
Announcement PDF
RNS Number : 8391R
Alba Mineral Resources PLC
31 October 2023
31 October 2023
Alba Mineral Resources Plc / EPIC: ALBA / Market: AIM / Sector: Mining
Alba Mineral Resources Plc
("Alba" or the "Company")
Investee Company Update
PEA Confirms Robust Economics for Amitsoq Graphite Project
Alba Mineral Resources Plc (AIM: ALBA) is pleased to note the RNS today by its portfolio company, GreenRoc
Mining Plc ("GreenRoc"), confirming the positive results of the independent Preliminary Economic Assessment
of its 100% owned Amitsoq Graphite Project in southern Greenland ("Amitsoq"). Alba has a 42.97%
shareholding in GreenRoc.
The GreenRoc announcement is set out below without material changes.
GreenRoc Mining Plc / EPIC: GROC / Market: AIM / Sector: Mining
31 October 2023
GreenRoc Mining plc
("GreenRoc" or the "Company")
Amitsoq Update
PEA Confirms Robust Economics for Amitsoq Graphite Project
GreenRoc Mining Plc (AIM: GROC), a company focused on the development of critical minerals projects in
Greenland, is pleased to announce the extremely positive results of the Preliminary Economic Assessment ("PEA")
of its 100% owned Amitsoq Graphite Project in southern Greenland ("Amitsoq") (Figure 1). The PEA was completed
to internationally recognised NI 43-101 standards by SLR Consulting Ltd ("SLR"), an independent UK consulting
firm with considerable global expertise in the field of mining and mineral processing, including in Greenland.
Highlights
·
Pre-Tax Net Present Value at 8% discount rate (NPV8) of US$235M with Internal Rate of Return (IRR) of 31.1%.
·
After-tax NPV8 of US$179M with IRR of 26.7%.
·
Life of mine (LOM) is 22 years with potential to extend through resource expansion.
·
4-year payback period on capital from start of production.
·
Average Net Revenue of US$89.8M per year throughout the 22-year LOM.
·
Total gross revenue of US$2.1Bn over a 22-year LOM, with total undiscounted net pre-tax cash flow totalling
·
Initial capital cost (Capex) of US$131M inclusive of 25% contingency.
·
Average operating cost (Opex) of US$121 per tonne of milled ore.
·
Average annual production of 77,000t of concentrate at a minimum 94% grade.
·
Mine plan assumes mining from the Lower Graphite Layer (LGL) only, leaving considerable resources from the
US$794.7 M.
Upper Graphite Layer (UGL) available for future production expansion or extension to the LOM.
The strong economic results from the PEA provide independent validation of the Project's potential to become a
globally significant producer of graphite concentrate. Simultaneously, GreenRoc continues to advance its
objective of developing the processing capabilities to upgrade its future graphite concentrate production into
anode material for electric vehicle ("EV") batteries, which the Company believes will add substantially to the
positive economics of the Amitsoq Project.
With a substantial graphite supply deficit being forecast for the coming decades, and the risks associated with the
global EV supply chain's overreliance on Chinese graphite highlighted by China's recent announcement of export
restrictions on battery-grade graphite, Amitsoq is positioned to become a key source of the high purity spherical
graphite required to produce anode material for the European car industry.
Stefan Bernstein, GreenRoc's CEO, commented:
"We are extremely pleased with the outcome of the PEA, which confirms robust economic figures for mining activities at
Amitsoq. A pre-tax NPV of US$235M with an IRR of 31.1%, initial CAPEX of US$131M (inclusive of a conservative 25%
contingency) and average Opex of US$121 per tonne of milled ore equates to a four-year payback on capital from start of
production, a healthy return on investment when set against an undiscounted net pre-tax cash flow totalling US$794.7 M
over a 22-year life of mine.
"The mine plan set out in the PEA is relatively straightforward thanks to Amitsoq's simple ore body geometry. All of the onsite processing equipment is based on the use of standard and proven techniques, but with potential upside through the
use of some new, and more efficient, processing technologies that we are currently exploring.
"The entire mining operation is planned to take place in the Lower Graphite Layer, thus reserving the Upper Graphite Layer
for production expansion, or to extend the mine life. About 75% of the mined ore in the PEA is sourced in the Measured and
Indicated category and, given the simple ore body geometry, we are confident that the remaining ca. 25% can be
upgraded into the higher confidence resource categories.
"The proposed use of a Drift and Fill mining method, coupled with the exceptionally high grades of the Amitsoq ore, will
mean that as much as 86% of the tailings will be used as backfill, with a mere 14% required to go to a tailing storage
facility. This is excellent news as it will minimise the environmental impact of the mine, whilst also saving the cost of
transporting tailings.
"While the PEA is based on the use of conventional diesel-generated power, we are looking into a variety of emission-free
energy solutions to replace the diesel-generated power plants as soon as that is feasible.
"China's announcement in the past few days of its imminent imposition of export restrictions on Chinese battery-grade
graphite provides the perfect backdrop to the release of the Amitsoq PEA and flags up the increasing strategic importance
of Amitsoq to the European and North American battery supply chain. This PEA provides independent validation of our
focus and determination to get the Amitsoq mine up and running in the shortest time possible while, at the same time,
developing graphite anode material processing capability through our recently initiated Anode Feasibility Study in
conjunction with the UK's Advanced Propulsion Centre. I am confident that the Anode Feasibility Study will, in due course,
provide further upside to Amitsoq and for our investors."
A map of land with blue lines and red squares Description
automatically generated
Figure 1:
Location
of
Amitsoq
deposit,
with
GreenRoc's mineral exploration licences
shown in blue (MEL 2013-06) and yellow
(MEL 2022-03).
Details
The PEA report contains a detailed
description of the ore bodies at
Amitsoq
and
incorporates
the
Competent Person Report (CPR) on
the resource estimate, an analysis of processing work and basic design of an on-site processing plant as well as
mine plan, workforce needs, capital cost (Capex) and operating costs (Opex) and a discounted cash flow (DCF)
model.
Mine Plan
The mine plan is based on 22 years of production with the full mining rate of 400,000t per annum reached after
two years of ramp-up.
The total mined inventory is 8.26Mt of ore with an average of 21.3% graphite (Cg). This is based on the mining
resource category given in Table 1 showing that the higher resource categories (Measured and Indicated) account
for about 75% of the mine mass. Cut-off grades are calculated at 18.7% Cg. The higher grades of 21.3% Cg versus
the average grade of 20.41% reported as average in the global resource estimate of January 2023 reflect that all
mining takes place in the LGL, where higher average grades have been recorded to date than those in the UGL.
The fact that the mine design in the PEA assumes production from the LGL only and is modelled on a total mining
inventory of 8.26Mt compared to a total January 2023 global resource estimate of 23.05Mt, is indicative that there
is significant potential for future production expansion and/or extension to the LOM at Amitsoq.
Table 1: LGL Mining Inventory by Mineral Resource Category
A table with numbers and text Description automatically generated with medium confidence
The proposed mining method is Drift and Fill, which requires backfill as the working platform. One central
spiralling decline will provide access to all mining levels from the deepest level of 320m below sea level to the
highest at 10m above sea level. The mining will be completed using a fleet of diesel-powered, electro-hydraulic drill
jumbos, bolters, load-haul-dump machines, and underground fitted trucks.
Mine Design
The underground workforce will be comprised of three crews on a four-week on, two-week off roster. The on-shift
workforce at Amitsoq will total 45 persons (so, 135 workers in total across the three crews) and mine support and
administrative staff at the nearby town of Nanortalik will total a further 19 persons per shift (for a total of 37
personnel).
Mined ore will be transported to a processing plant on site, crushed by a conventional three-stage crushing circuit
and then ground by ball mills to produce a slurry with optimum size distribution for concentration in flotation
units. The final filter-pressed concentrate product will have a minimum content of 94% graphite. It will be stored
in 1t bulk bags before transportation to Nanortalik town for later shipment to the designated overseas port of
destination.
Tailings from the processing plant will primarily be used for backfill in the mine. With an annual nominal mining
rate of 400,000t, ca. 3.8M m3 of tailings will be produced throughout the life of the mine (LOM), of which ca. 3.3M
m3 will be used as backfill with ca. 0.5M m3 remaining for surface storage. A number of options have been
considered for the storage of the relatively modest volume of tailings, including both dry-stack and wet storage
facility in a nearby dead (not life-supporting) lake. Transport to the storage facility is planned to take place on
barges.
Project infrastructure
Most of the infrastructure required to run the mine will be situated at the mine site. In addition to the processing
plant, backfill paste plant, workshops and storage space, the infrastructure will include a T-shaped pier for
accommodating ships, accommodation for day and night shifts, a catering and recreation complex (for a total of
up to 110 people at any given time), freshwater treatment for water supply based on reverse osmosis, wastewater
treatment, tailings load-out area, power generation plant, short-term fuel storage and an emergency treatment
medical facility.
Electric power for the mine, process plants, and infrastructure on the island will be produced from diesel-fuelled
generator sets. The estimated power demand for the island is 11 MW. Five operating 2500 kVA generators plus
one stand-by unit will provide the power. Electric power for the tailings area will be provided from a small 300 kW
diesel generator. At the same time, the Company is investigating the means to transition to zero-carbon
electricity generation as soon as it is feasible to do so.
The main fuel depot will be located at the nearby town of Nanortalik (20km from the mine), where warehouse and
office space will be rented partly, or wholly, using existing structures for marshalling, storage and administrative
purposes. Nanortalik harbour, which has ice-free conditions through the winter, will be the base for the shipping
of graphite concentrate to the designated ports of destination, which are expected to be either northern Europe
(4-5 days of shipping) or North-East America (5-7 days of shipping).
Project Economics
Initial Capex (for construction and commissioning) amounts to a total of US$131M which includes 25%
contingency of US$26M (Table 2).
Operating costs amount to US$111/t milled ore and break down into mining costs of US$53.9/t, processing costs
of US$24.5/t and general & administration (G&A) (supporting costs (transport, backfill paste etc) of US$32.7/t (see
Table 3), plus US$10/t to cover shipping of concentrate to port of destination for a total of US$121/t.
Total gross revenue amounts to US$2.1Bn over a 22-year LOM, with the total undiscounted net pre-tax cash flow
(i.e., total revenues less total Capex, Opex and other costs and charges) totalling US$794.7 M. This is based on an
average basket graphite price of US$1250/t of 94% concentrate, based on the forecast average for 2028-2033
published by Fastmarket in May 2023.
This results in a pre-Tax Net Present Value at an 8% discount rate (NPV8) of US$235M with an Internal Rate of
Return (IRR) of 31.1%. The after-tax NPV8 is US$179M with an IRR of 26.7% (see Table 4, which also gives the NPV
at 6% and 10% discount rates).
A table of cost Description automatically generated
Table 2: Specification of Capital Costs
A white and green rectangular box with black text Description
automatically generated
Table 3: Specification of Operating Costs
Table 4. Amitsoq project economic performance with varying discount rates at 6, 8, and 10%. The After-Tax NPV and IRR
includes 2.5% royalties to the Greenland Government.
Discount rate
Pre-Tax IRR
Units
%
Value
31.1%
Pre-tax NPV at 6% discounting
6.0%
US$ '000
$314,441
Pre-tax NPV at 8% discounting
8.0%
US$ '000
$235,308
Pre-tax NPV at 10% discounting
10.0%
US$ '000
$177,115
After-Tax IRR
%
26.7%
After-tax NPV at 6% discounting
6.0%
US$ '000
$243,663
After-tax NPV at 8% discounting
8.0%
US$ '000
$179,353
After-tax NPV at 10% discounting
10.0%
US$ '000
$132,224
Forthcoming work activities
In the light of the resoundingly positive independent economic assessment provided by the PEA, GreenRoc
remains committed to pushing forward the Amitsoq graphite project to production as fast as possible.
A large bulk ore-sample of 10-20t will be collected from the old underground workings at the Amitsoq mine and
shipped to independent processing laboratories in Europe. This will enable further design processing parameters
to be determined and provide material both for pilot-scale active anode material processing and for ongoing
analysis by interested offtake and strategic partners.
A Phase III drilling programme is planned for 2024, which will provide further expected upgrades to the graphite
resource as well as key geotechnical data to feed into the Pre-Feasibility Study (PFS) which is planned to
commence in H2, 2024. The PFS will build upon the PEA by undertaking detailed engineering in order to optimise
mine and processing design and further constraining the mining inventory, capital and operating cost estimates
and other economic design parameters.
2024 will also see the completion of the Environmental and Social Impact Assessments for Amitsoq and the
submission of an application for an Exploitation Licence, further key milestones in the route to commercial
production.
Lastly, in parallel with the development work at the Amitsoq graphite mine, GreenRoc is conducting a Feasibility
Study on a graphite anode material processing plant, using specialist subcontractors Benchmark Mineral
Intelligence, ProGraphite, SLR and Decision Risk Analytics and supported by a £250k grant from the Advanced
Propulsion Centre (see RNS Oct 9, 2023). The Feasibility Study is planned to be concluded in Q2, 2024.
This announcement contains inside information for the purposes of the UK Market Abuse Regulation and the
Directors of the Company are responsible for the release of this announcement.
Forward Looking Statements
This announcement contains forward-looking statements relating to expected or anticipated future events and anticipated
results that are forward-looking in nature and, as a result, are subject to certain risks and uncertainties, such as general
economic, market and business conditions, competition for qualified staff, the regulatory process and actions, technical
issues, new legislation, uncertainties resulting from potential delays or changes in plans, uncertainties resulting from
working in a new political jurisdiction, uncertainties regarding the results of exploration, uncertainties regarding the timing
and granting of prospecting rights, uncertainties regarding the timing and granting of regulatory and other third party
consents and approvals, uncertainties regarding the Company's or any third party's ability to execute and implement
future plans, and the occurrence of unexpected events.
Actual results achieved may vary from the information provided herein as a result of numerous known and unknown risks
and uncertainties and other factors.
Competent Person Declaration
The independent Competent Person for the disclosure of the results of the Amitsoq Project Preliminary Economic
Assessment (PEA) is Mr Bryan Pullman, P.Eng. of SLR Consulting Limited. Mr Pullman has reviewed and approved
the technical content of this news release insofar as it reflects the PEA, in the form and context in which it appears.
Mr Pullman completed a site visit to the Amitsoq Project on 27 May 2023 and visited locations relevant to the
Project including the underground workings, and potential process plant, and other infrastructure sites within the
licence area.
**ENDS**
For further information, please visit www.albamineralresources.com or contact:
Alba Mineral Resources Plc
George Frangeskides, Executive Chairman
+44 20 3950 0725
SPARK Advisory Partners Limited (Nomad)
Andrew Emmott
+44 20 3368 3555
CMC Markets plc (Broker)
Thomas Smith / Douglas Crippen
+44 20 3003 8632
Alba's Projects and Investments
Mining Projects Operated by Alba
Location
Ownership
Clogau (gold)
Wales
100%
Dolgellau Gold Exploration (gold)
Wales
100%
Gwynfynydd (gold)
Wales
100%
Investments Held by Alba
Location
Ownership
GreenRoc Mining Plc (mining)
Greenland
42.97%
Horse Hill (oil)
England
11.765%
This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct
Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of
this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information
contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services.
For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy
Policy.
END
PFUFIFIDIELLVIV
Share your feedback
Discover